SIMONTON CONSTRUCTION CO. et al. v. POPE et al., 213 Ga. 360, 99 S.E.2.d 216 (1957)

Supreme Court of Georgia

Linked as:

Text


Shirley C. Boykin, D. B. Howe, Guy Parker, Harry S. McCowen, A. B. Parker, contra.Robert D. Tisinger, William J. Wiggins, for plaintiffs in error.

1. Both the request to review and overrule Simonton Construction Co. v. Pope, 212 Ga. 456 (93 S. E. 2d 712), and the request that we require the entire case in the Court of Appeals to be sent to this court, and that we determine all issues in the case, are denied.

2. No legal judgment can be rendered in a law case where exceptions of fact filed therein to an auditor's report are not referred to a jury where there is not an express waiver of a jury. The exception to the antecedent rulings refusing requests that issues of fact be referred to a jury, subjects the final judgment which is excepted to to a review upon the grounds covered by the antecedent rulings, and those antecedent rulings, being a denial of requests for a jury, bring for review the ruling refusing to refer the exceptions of fact to a jury.

3. A clause in the contract between the owner and the contractor which provides that the contractor must give notice within a limited time to the subcontractor of claim for materials and labor furnished the subcontractor, but not appearing in the subsequent contract between the contractor and subcontractor can not be invoked by the subcontractor to defeat the claim of the contractor for the costs of finishing the work after the subcontractor breached his contract and abandoned the job before it was completed.

4. Irrespective of how sharply other evidence may have contradicted the joint letter of plaintiff Pope and W. I. Lanier, to the defendant, in which defendant was notified that as of that date, July 1, 1954, W. I. Lanier was taking over the contract, and all funds accruing thereunder should be the property of W. I. Lanier, the other evidence did not demand a finding contrary to this letter, but could only raise an issue of fact.

Certiorari to Court of Appeals -- 95 Ga. App. 211.

This case was transferred to the Court of Appeals as one at law and not in equity by this court as reported in Simonton Construction Co. v. Pope, 212 Ga. 456 (93 S. E. 2d 712). Thereafter, the Court of Appeals affirmed the judgment "on condition," and the plaintiffs in error applied for a writ of certiorari which was granted. The case is now before this court on three grounds of alleged errors of the Court of Appeals as reported in Simonton Construction Co. v. Pope, 95 Ga. App. 211 (97 S. E. 2d 590). Exception to the ruling of the Court of Appeals in headnote and division 4a of the opinion holding that the plaintiffs in error waived a trial by jury of the exceptions of fact to the auditor's report is dealt with in headnote and division 2 of this opinion. Alleged error in division 3b of the opinion holding that certain provisions of the prime contract inured to the benefit of the subcontractor is considered in headnote and division 3 of this opinion; and alleged error in division 2 holding that the pleadings and the evidence demanded a finding that a third party was not the assignee of the sub contract is considered in division 4 of this opinion.

1. Defendant in certiorari Pope has filed a motion in this court that we review and overrule the decision in Simonton Construction Co. v. Pope, 212 Ga. 456 (93 S. E. 2d 712), and that we, acting under powers conferred by the Constitution, Code (Ann.) 2-3704, require the entire record in this case be transmitted to the Supreme Court in order that this court may hear and determine all legal issues in the case. Even if it were not the law of the case, which prevents our overruling the decision referred to, we would not overrule it because it is a sound and correct interpretation of the pleadings and the law. We will not review or decide any questions in this case that have not been brought by the petition for certiorari to this" court for review. Therefore, the motion is denied.

Poullian v. Brown, 206 Ga. 808 (58 S. E. 2d 834). With the final judgment thus brought under review upon the specific ground that a request for a jury trial was denied, the Court of Appeals erred in ruling that no error was assigned on the denial of a jury trial and that a jury trial was waived. Error is assigned, and it shows reversible error in denying the request for a jury.

This record shows beyond question that the setoff claimed is mainly for services rendered and materials furnished by the contractor to himself, and not the subcontractor, in finishing jobs abandoned by the subcontractor before completion. If the defense is true, and it must be so considered in deciding this question, there had ceased to be a subcontractor and the contractor was fulfilling his obligation to the owner to finish the jobs. After the breach of contract by the subcontractor no contractual relationship existed. The amount of the setoff is what the subcontractor lacked of earning the contract price for completing the jobs. He could not lawfully recover the full amount without proving completion of the work. It would be both unjust and unlawful to allow the subcontractor to collect for work and materials he contracted to furnish but failed to furnish. The court erred in ruling that the above quoted paragraph of the contract between the owner and the contractor inured to the benefit of the subcontractor and barred the defendant's setoff.

4. The other and final assignment of error is upon the court's ruling as follows: "Since the pleadings and evidence demanded a finding that Lanier, a third party, was not an assignee of the plaintiff's contract and rights accruing thereunder, and was not in fact understood by the parties to be such assignee, the trial court did not err in either overruling an exception to a finding of the auditor refusing to adjudicate that plaintiff had no right to prosecute the action in his own name, and also in refusing to recommit the case to the auditor on this question." The complaint is that the Court of Appeals here makes a finding of fact which the auditor refused to do and that such finding is incorrect. There is in the record the evidence of a written instrument addressed to this defendant and signed by both the plaintiff Pope and W. I. Lanier, dated July 1, 1954, and containing the following clauses: "you are advised that pursuant to a contract between the undersigned parties, D. G. Pope and W. I. Lanier, dated December 17, 1953 with which you are familiar, it has been apparent for some time that it would be necessary for W. I. Lanier to take over the contract of Pope Plumbing Company with you. [Elsewhere in this letter the contract is shown to be the one here involved.] Pursuant to the provisions of the contract between the parties; and as of this date W. I. Lanier is taking over that contract and will assure performance of the obligations of Pope Plumbing Company, and all funds accruing for said performance shall be as of this date the property of W. I. Lanier, subject to the terms of said contract, and this action is taken to protect performance of the subcontract and the bond for completion thereof, and to assure application of the contract price to the discharge of material and labor claims. You are notified accordingly." We do not have the testimony of witnesses, or other evidence, and even though it sharply contradicts this writing it could not demand a finding contrary to the provisions of this letter, and therefore, the court erred in so ruling.

For the reasons stated in this opinion the judgment of the Court of Appeals is reversed.

Judgment reversed. All the Justices concur, except Wyatt, P. J., who is disqualified.

1957

Sponsored links




ver las páginas en versión mobile | web

ver las páginas en versión mobile | web

© Copyright 2012, vLex. All Rights Reserved.

Contents in vLex United States

Explore vLex

For Professionals

For Partners

Company